Project References

Substation Maintenance, Halkirk Wind Farm

Overview

Capital Power's Halkirk Wind Farm is a 150-megawatt power generating facility located in Central Alberta. With 83-turbines, it is one of the largest of its kind in the province, capable of producing power for up to 50,000 homes.

Magna IV Engineering performed maintenance testing and inspections on the medium and high voltage equipment at the windfarm's 230kV/34.5kV substation. This testing and inspection included all of the primary 230kV and 34.5kV equipment along with the protection relaying for the collector circuits and main power transformer.

Location

Halkirk, Alberta, Canada

Year Completed

2014

Value

$68k

Tags

Technical Field Services, High Voltage Testing, Substation, Electrical Maintenance

Categories

Utility, Power